Kitchen before:
Day 1 of renovations: Removing doors, appliances, trim, and china cabinet:
On Day 2 CD, Papa and Brian ripped out our cabinets, making it dusty!
Black Friday was spent installing a sliding glass door, ripping out sheetrock, and then the rest of the tile floor.
Before sliding door:
During:
After!
A week later Brian, Papa and I rewired the entire room and added insulation:
Sheetrock started after that:
We added a new window because the floors were going to bring the new countertops too high:
Next came knockdown texture and new can lights:
By day 19 we were ready for paint:
Day 20: Floor tile
After paint, day 22 began with cabinets!
Day 26: Appliances
Papa cleans out our garage..
Hooking up our new stove:
Done!
Waiting on counters (January 7th), cabinet crown, and backsplash!